East Side Access under Grand Central Terminal:

�Brings the Long Island Rail Road to Manhattan’s East Side, with 160,000 passengers a day arriving at the new, eight-track Grand Central hub 16 stories below Grand Central Terminal.

�To be completed by 2019.

�Estimated cost is $8.3 million.

No. 7 extension to Manhattan’s West Side:

�Links Times Square to the far West Side to attract development to Manhattan’s “last frontier” of available land and the Hudson Yards development.

�To open in 2014.

�Estimated cost is $2.1 billion.

Second Avenue Subway on Manhattan’s East Side:

�Eases massive congestion on Lexington Avenue subway lines and opens far East Side to commuters.

�First section to open in 2016.

�Estimated cost for first phase is $4.5 billion.